Weak areas only fix themselves when you can see them: every simulated C-S4CPS-2105 session at GuideTorrent ends with a score, letting you target the SAP Certified Application Associate - SAP S/4HANA Cloud (public) - Professional Services Implementation domains that need hours instead of spreading them evenly and hoping.
SAP C-S4CPS-2105 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Resource Management | 14% | - Capacity and utilization monitoring - Time recording and confirmation - Resource requests and staffing |
| Sales and Billing for Professional Services | 18% | - Fixed-price, time and expense billing - Billing due list and invoice creation - Revenue recognition and integration with FI |
| Project Management and Cost Control | 22% | - Cost posting, allocation, and settlement - Internal and customer project creation - Project planning, budgeting, and forecasting - Project reporting and analytics |
| Data Migration and Integration | 10% | - Integration with S/4HANA Cloud core - Migration cockpit and templates - Data load and validation |
| Extensibility and Configuration | 12% | - Self-Service Configuration UIs (SSCUI) - Fiori app configuration - Custom fields and logic |
| Organizational Structure and Master Data | 12% | - Customer and supplier master data - Project types, cost centers, profit centers - Service organization, company code, controlling area |
| SAP Activate Methodology and Cloud Implementation | 12% | - Explore, Realize, Deploy phases - Fit-to-Standard workshops - Starter and Quality systems |
C-S4CPS-2105 Exam Questions Answered by GuideTorrent
- Project Management and Cost Control (22%)
- Organizational Structure and Master Data (12%)
- Resource Management (14%)
SAP Certified Application Associate - SAP S/4HANA Cloud (public) - Professional Services Implementation Sample Questions:
In the SAP Best Practices Time Recording - Project-Based Services (J12) scenario, which of the following settings can be enabled via SSCUI Maintain Data Entry Profiles? Note: There are 3 correct Answers to this question.
- A. Enable the field 'Work Location' to allow users to enter work location when recording the time in timesheet application
- B. Switch on the field 'All Project Phases' to enable timesheet posting to be made regardless of project status
- C. Enable the field 'WBS Element' to allow users to specify the project task they are recording time against
- D. Switch on or off the approval process
- E. Switch on the field 'Extensibility Mode' to enable the extensibility of the timesheet application
Correct Answer: A,D,E 🗳️
What are the steps for conducting automated business process testing? Note: There are 3 correct Answers to this question.
- A. Assess data management
- B. Create a test system
- C. Correct and rerun failed test processes
- D. Run the test
- E. Create a test plan
Correct Answer: C,D,E 🗳️
Which of the following business roles are required to analyze the Margin & Work Analysis for Projects?
Note: There are 2 correct Answers to this question.
- A. Analysis Accountant
- B. Margin Analyst
- C. Analytics Specialist
- D. Project Manager - Commercial Services
Correct Answer: C,D 🗳️
How is the project sales order created for customer engagements?
- A. Manually after creating the customer project
- B. Automatically after setting the project to "in execution"
- C. Automatically after maintaining project billing
- D. Manually before creating the customer project
Correct Answer: C 🗳️
Which of the following KPI cards in the advanced version of Fiori app Resource Management for Projects allow you to access the Manage Project Staffing app? Note: There are 2 correct Answers to this question.
- A. Open Resource Requests
- B. Staffed and Required Hours by Role
- C. Average Resource Utilization
- D. Resources with Free Capacity
Correct Answer: A,D 🗳️